House Update
The quick and dirty version:
- we have a new roof
- rough plumbing is in, inspected and approved
- tub has been set
- remainder of floor has been closed in
- framing in siven, addie's and bathroom is done (with the exeception of some nailers)
- framing in front play area still needs to be complete
- have a quote and are accepting it to have the insulation done
- siven wants jesse to pick up a paint brush and green watercolors so he can paint his room
- upstairs electrical panel to be set this weekend
- all outlet and switches have been located
- electrical wiring to commence this weekend
front play area
bathroom, which now has a floor and walls